Servelec Controls has provided control and safety systems for Centrica’s producing assets for over 25 years and to this day continues to provide ongoing service support and system upgrades to all those assets now operated by Spirit Energy.

One such project saw the upgrade of the obsolete safety equiment on the DPPA platform, completing a series of fire and gas system (FGS) and emergency shutdown (ESD) system upgrades on all the assets across Morecambe Bay.

Minimised Downtime

The new systems are not only more reliable, but by simplifying the technology, diagnosis times of now unlikely issues are greatly reduced.

Since DPPA is a processing platform, the programme of works also had to minimise disruption to routine operation in order to avoid affecting production from adjacent fields.

Improved system reliability and minimised downtime

Reduced maintenance and proof testing requirements

Reduced spares holding through system consistency across the field

 

The Old Systems

Centrica had identified that the existing GE Fanuc 90/30 programmable logic controller (PLC)-based emergency shutdown (ESD) and fire and gas safety (FGS) systems utilised obsolete technology. They also incorporated complex and unreliable hardwired back-up relay systems and operator interface matrices for status indication and test functionality, making them maintenance intensive and liable to calibration drift, causing loss of production through unplanned platform shutdowns.

Integrated Solution

Servelec Controls provided a new GE-based ESD system supplied on backplanes so that it could be directly mounted into the existing offshore control room cabinets.

The new GE-based FGS, which included Simtronics, Honeywell, Det-tronics and Siemens gas, flame and smoke detection devices, was built and housed in new cabinets provided by Servelec Controls.

Both systems were hardwired into existing platform equipment and interfaced with the existing distributed control system (DCS) as well as remote systems on neighbouring platforms. Servelec Controls also provided a new Wonderware InTouch based HMI for operator interfacing, providing historical alarms, events and data plus access to sequence-of-events recording, inhibit and override control.

.. 

Flexible Installation Programme

Following a detailed design phase, Servelec Controls first began installation and precommissioning of the new fire and gas detection devices in May 2016, followed by installation of the new emergency shutdown system in August, all in line with client shutdown schedules.

From initial isolation and destruct to Lloyds verification testing and sign-off, actual downtime amounted to just three weeks.

The obsolete equipment was then decommissioned and deconstructed during scheduled intervention windows over the next six months.

Field Wide Deployment

The solution was based on the same, proven systems that Servelec Controls previously deployed across all the other assets in Morecambe Bay, providing consistency for maintenance and operator understanding, plus uniformity of spare parts.

Ongoing Support

Servelec Controls continues to provide ongoing system support and maintenance to Spirit Energy’s Morecambe Bay onshore and offshore assets. As well as holding a supply of spares specifically for the Morecambe Bay systems, Servelec Controls provides Spirit Energy with regular scheduled site inspections and 24 hour on call service.

Case Study : Morecambe Bay DPPA Platform ESD and FGS Replacement

Download a pdf of the Morecambe Bay DPPA case study here

Related Case Studies

Easington Fire & Gas System

Following the success of a £1.5million Emergency Shut Down system, Servelec Controls was commissioned to provide Easington with a new Fire & Gas System

Emergency Shutdown Control System at the North Morecambe Terminal

The Barrow Terminal Optimisation Project (BTOP) was a phased period of work completed in September 2015 through which the two Centrica gas terminals at Barrow-i…

Centrica Emergency shutdown (ESD) safety system

Servelec Controls designed, implemented and commissioned an emergency shutdown (ESD) safety system as part of Centrica Storage’s York field development project …